Tuesday, June 12, 2012

It's the beginning of a building!

In the last couple of weeks the focus has been on roughing in the underground plumbing and electric. Footings have been poured for the main building, dumpster, and the sign. This week we will begin to pour the main slab.  The masonry and walls are scheduled to start going up on June 18th. This will take about 4 weeks. When that is finished, we will begin to erect the steel.

No comments:

Post a Comment